How Much Concrete Do I Need for a 10×10 Slab?
A 10×10 ft slab at 4 in thick is 33.33 ft³ = 1.23 cubic yards. At 0.60 ft³ per 80-lb bag that is 56 bags before waste (62 with 10%). Use the Concrete Slab Calculator for your exact dimensions.
Ready to run the numbers? Use our Concrete Calculator or the Concrete Slab Calculator to get an instant material estimate.
The quick answer
A 10×10 ft slab is 100 ft². Volume = length × width × thickness: 10 × 10 × (4÷12) = 33.33 ft³ ÷ 27 = 1.23 yd³ before waste. With 10% waste you order about 1.36 yd³. Bag count at 0.60 ft³ per 80-lb bag: 33.33 ÷ 0.60 = 56 bags before waste, or 62 bags with 10%. That is past one cubic yard, so ready-mix delivery is usually cheaper than mixing ~60 bags by hand.
- 4 in thick — 33.33 ft³ = 1.23 yd³ (56 eighty-lb bags at 0.60 ft³) before waste; ~1.36 yd³ / 62 bags with 10%.
- 5 in thick — 41.7 ft³ = 1.54 yd³ (70 bags) before waste; ~1.70 yd³ / 77 bags with 10%.
- 6 in thick — 50.0 ft³ = 1.85 yd³ (84 bags) before waste; ~2.04 yd³ / 92 bags with 10%.
How thickness changes the number
Thickness is the single biggest driver of concrete volume, because it multiplies the entire 100 ft² footprint. Going from 4 in to 6 in adds 50% more concrete — and 50% more cost. Use 4 in for foot-traffic patios and shed pads, 5 in for heavy furniture or fire pits, and 6 in if the slab will ever see a vehicle.
Source: 1 cubic yard = 27 cubic feet. Thickness in inches ÷ 12 converts to feet.
10×10 at 4 in: 10 × 10 × (4÷12) = 33.33 ft³ ÷ 27 = 1.23 yd³. With 10% waste: 1.23 × 1.1 = 1.36 yd³ to order.
Bags vs. ready-mix delivery
Under about 1 cubic yard (~45 eighty-lb bags), bagged mix can be practical. A 10×10 at 4 in is already ~56 bags before waste — past that line for most DIYers — so ready-mix delivery is usually cheaper and far less labor. At 6 in you are over 2 yards. Schedule the truck and a crew of at least two ahead of time.
Base, forms and finishing tips
- Pour on 4–6 in of compacted gravel (3/4 in crushed stone with fines packs best).
- Set 2×4 forms level and staked every 3–4 ft; the slab is only as flat as the forms.
- Add wire mesh for a 4 in slab, or #4 rebar on 24-in centers for 5–6 in slabs.
- Cut control joints every 8–10 ft so the slab cracks where you want it to.
- Cure slowly — mist and cover with plastic for at least 7 days for full strength.
Frequently asked questions
How many bags of concrete do I need for a 10×10 slab at 4 inches?
33.33 ft³ ÷ 0.60 ft³ per bag = 56 eighty-pound bags before waste, or 62 bags with a 10% allowance. Confirm the yield on your bag label — brands vary slightly.
How many cubic yards is a 10×10 concrete slab?
1.23 yd³ at 4 in thick, 1.54 yd³ at 5 in, and 1.85 yd³ at 6 in — before waste. Add 10% for spillage and uneven subgrade.
Should I use bags or order ready-mix for a 10×10 slab?
At 4 in (about 1.2 yards) bags are workable with a mixer. At 5–6 in you are over 1.5 yards, where delivered ready-mix is usually cheaper and much less labor.